Chapter- 10 Time, Procedure and Place for Performing Contracts

Section 71: Times and Procedure of performing contract

Estimated reading: 1 minute 30 views

1) In case the time and procedure of performing the contract has been mentioned in the contract, it shall be performed within the specified time and according to the specified procedure.

2) In case no time or procedure for performing the work mentioned in the contract has been specified, whereas in case the work can be performed only at any specific time or according to any specific procedure, the contract shall be deemed to have been concluded so as to perform the work at that time and according to that procedure.

3) Except in the circumstances mentioned in sub-section (2), in case the time and procedure of performing the contract has not been mentioned in the contract, the contract shall be performed within a reasonable time by adapting a reasonable procedure.

Share this Law

Section 71: Times and Procedure of performing contract

Or copy link

Discover Nepal's laws effortlessly. Our user-friendly platform simplifies legal understanding and accessibility, serving individuals throughout the country.